* Burner with fuel, mono-bloc casting guiding type with horizontal flame, lighting and safety of electronic ignition, permanent ventilation, electromagnetic sluice gate of regulation and isolating valve.
* A secondary injection of air to ensure perfect oxygen content.
19.    A control box ensuring the complete cycle of combustion.

20.    Fan:
* Electro-ventilator distributing the secondary air, the regulation of the air flow being carried out by valves and following the control of the automatic cycle.
21.    Controls and regulations:
Control box watertight to dust, including:

* A switch circuit breaker for each engine (ventilators and burners).
* A timer with adjustable temporization for the regulation of each burner.
* A regulator with digital watching for the temperature of combustion.
* A regulator with digital watching for the temperature of postcombustion.
* Electric box.

21. The de- ashing must be done in the bottom of the combustion chamber or the deashing should be Automatic or manual batch de ashing.
22. Process Filtering system : Scruber to be mentionned as optional
23. Emission Standards Compliance: BS 3316 or équivalent standard
23. Capacity to treat Plastic: Not less than 40% by weight
24. CE Manufacturing Compliance: BS EN 746-2-1997
22.    The supplier must give batches of spare parts of first urgency and consumable of the incinerator.
23.    The installed incinerator must bear a one year guarantee.
24.    The supplier shall perforn an onsite installation of the incinerator.
25. The technical training of operators will have to be provided and given by a technician from
the factory; it will consist of curative and preventive maintenance, and the use of machine, etc

NB.: Civil works and any other related services for the installation and training of operators must be included in the incinerator’s price.
Specification for the shelter of the incinerator: House of the incinerator inclusive in offer (the house must have facilities for hand washing and firefighting).
This material and equipment must include in the shed of the incinerator: foundation in rubble stone, isolation roofing against humudity; elevation with brick of 20 cm (bloc cement), continuing lintel (linteau) in reinforced concrete; steel frame (charpente en metal); roofing in sheet B.C.A. 28 BG (Toiture en t?le),metal gutter, sanitary installation (wash basin, soakway pit of 20 m of depth); ash pit of 30 m3,electrical installation; concrete slab for fixing the incinerator; chanel for evacuation of rain water or waste water, wire mesh for aeration up the lintel; smooth rougtcasting of walls (interior and outside);plinth with cement; 2 metal doors ;email paintings inside and latex paintings outside the house on walls and on doors; roofing limit (planche de rive); measures for this specification will depend on the size of the incinerator which will determine the size of the shed of the incinerator., etc

HICLOVER is growing brand for environmental protection field, and market share with most of Africa, Middle East, Southeast Asia countries and part of North America, Europe territory. We are trusted partner for governmental organizations, non-profit organizations, international contractors, logistics organizations, military, pet cremation business owners, etc. We have export experience more than 40 countries, including war zone like Iraq, Afghanistan, Somalia, South Sudan. Mobile: +86-13813931455(WhatsApp) Website: www.hiclover.com Email: sales@hiclover.com Email: hicloversales@gmail.com